Home Corporate Procurement Plan 2025 – 2027

Corporate Procurement Plan 2025 – 2027

Corporate Procurement Plan 2025 – 2027

Date published: February 2025


1.     Introduction

The Code of Practice for the Governance of State Bodies 2016 (the Code) requires state bodies to prepare a Corporate Procurement Plan as set out in section 8.20 of the Code.

This plan sets out how the Authority undertakes its procurement functions in compliance with section 8.20 of the Code.

The Authority’s Statement of Strategy identifies good corporate governance and controls as a key enabler for achievement of the organisation’s strategic objectives and that a key outcome is to ensure full compliance with the Code of Practice for the Governance of State Bodies.

2.    Objective of the plan

The objective of this plan is to ensure the Authority’s ongoing compliance with EU and national procurement legislation, circulars, and guidelines (see Appendix 1).

3.    Procurement expenditure analysis

Appendix 2 provides an analysis of the Authority’s expenditure which is subject to, and not subject to, procurement.

The Authority publishes a full set of accounts in its annual report.

4.    Implementation of the plan

An overview of the implementation of this plan is set out under the headings below.

4.1    Management of procurement

The Operations Unit has responsibility for the procurement functions in the Authority which includes:

  • ensuring that all procurement meets EU and national directives, legislation, circulars, value for money and guidance requirements,
  • management of the procurement plan, policy, procedures and associated records,
  • management of finance and purchase management systems and procedures,
  • training for staff on procurement policies and procedures,
  • final approval for payment of all expenditure, and
  • support to staff on procurement which includes assistance with identifying appropriate procurement methods, the preparation of RFTs (requests for tender) and contracts, conducting evaluations, and providing feedback.

4.2    Procurement policy and procedures

The Authority’s procurement policy and procedures comprise the following elements:

  • Corporate procurement plan: this outlines the principles that govern the Authority’s procurement activities and is published on the Authority’s website.
  • Procurement procedures manual: this provides guidance on approval procedures, threshold levels, use of frameworks templates and contracts, purchase management and contract management. This also includes guidance on Green Public Procurement.
  • Corporate procurement register: this records the Authority’s procurement activity.

4.3    Oversight of the Authority’s procurement

To ensure appropriate oversight of the Authority’s procurement, the following corporate governance is in place:

  • Annual expenditure and budgets are set by management and reviewed by the ARC who in turn recommend them to the Board of the Authority for approval.
  • The SMT and the ARC review the management accounts on a quarterly basis. Part of this process is to report on any budget variances and comment on any procurement issues that arise and raise any concerns where relevant with the board of the Authority.
  • Approval by the Board of the Authority is required for the award of any one contract over €100,000 (ex VAT).
  • Ministerial approval is required for any expenditure above €55,000 (ex VAT) on consultants or advisers in accordance with Section 12 of the Pensions Act.
  • Appropriate prior approval is required for all procurement and purchasing activities.
  • End of year draft accounts are submitted to the Department of Social Protection and the Department of Finance.
  • Annual independent internal and Comptroller and Auditor General audits are conducted.

4.4    Procurement templates

The Authority will use Office of Government Procurement (OGP) frameworks where available and appropriate. Where an OGP framework is not available or deemed not appropriate, the Authority will procure goods and services in accordance with OGP guidelines.

For the procurement of services, the Authority will use its own suite of templates for requests for tender (RFTs) and contracts that are based on OGP templates.

For the procurement of ICT goods and services, the Authority will prepare RFTs and contracts on a case-by-case basis as recommended by the OGP.

4.5    Procurement action plan 2025 to 2027

The Procurement action plan sets out practical, time limited measures the Procurement team within the Operations Unit will undertake to improve routine procurement procedures. The Procurement action plan is set out in Appendix 3.

Appendix 1 – Procurement legislation and guidance

Included here is a list of relevant legislation and guidance that applies to procurement by the Authority.

Name Source Description Links
EU Directives
EU Directive on public procurement EU Directive and Irish regulations The current EU directive on public procurement implemented in Ireland via SI 284 of 2016. SI 284 of 2016 and Directive 2014/24/EU
EU Directive on procedures concerning the award of public contracts (the Remedies Regulations) EU Directive and Irish regulations These Regulations apply to all contracts above the EU threshold and oblige contracting authorities to provide minimum information to unsuccessful tenderers and to allow for a ‘standstill period’ of 14 days before execution of contracts. Under these Regulations, suppliers may challenge contract award decisions in the High Court. SI 130 of 2010 and Directive 2007/66/EC
OGP guidance
National Public Procurement Policy Framework OGP This document sets out the overarching policy framework for public procurement in Ireland. National Public Procurement Policy Framework (November 2019)
Template RFTs and Contracts for Goods and Services OGP OGP templates designed for tenders for low to medium risk goods and services that are above the EU threshold. OGP Templates for Goods and General Services
Public Procurement Guidelines for Goods and Services OGP This document provides comprehensive guidance on procurement processes for contracts, frameworks, above and below EU thresholds.  Public Procurement Guidelines for Goods and Services
Green Public Procurement (GPP) OGP Green Public Procurement (GPP) is a process where public authorities seek to source goods, services or works with a reduced environmental impact throughout their life cycle. Green Public Procurement (GPP)
OGP Information Notes OGP The OGP regularly publishes information notes providing guidance on specific matters such as ESPD, GDPR etc. OGP Information Notes
Irish government circulars and guidance
Code of Practice for the Governance of State Bodies DPER Sections 8.16 to 8.21 set out requirements for the Board and Chairperson in relation to procurement governance including:
  • procurement policies and procedures
  • corporate procurement plan
  • contracts database
  • procedures to detect non- compliance
  • obligation on Chairperson to report non-compliance.
Code of Practice for the Governance of State Bodies (August 2016)
Infrastructure Guidelines DPER In 03/2023, the Public Spending Code was replaced by the Infrastructure Guidelines. The Infrastructure Guidelines set out the value for money guidelines for the evaluation, planning and management of public investment projects in Ireland. Infrastructure Guidelines
Freedom of Information Model Publication Scheme DPER – FOI Central Policy Unit This document includes the requirements to publish procurement information under the FOI Act, 2014. Freedom of Information Model Publication Scheme (July 2016)
Determining Insurance Requirements for Goods & Services RFTs & Contracts State Claims Agency This document provides guidance on the appropriate types and levels of insurance cover for contractors in the performance of public contracts for goods and services. Guidance on Indemnity and Insurance
Arrangements for Oversight of Digital and ICT-related initiatives in the Civil and Public Service DPER This circular sets out the arrangements for oversight of digital and ICT initiatives in the Civil and Public Service and the additional arrangements that are in place in relation to Peer Review of digital and ICT Initiatives of significant scale, risk or strategic importance being undertaken in the Civil and Public Service. Circular 14/2021
Promoting the use of Environmental and Social Considerations in Public Procurement DPER The purpose of this Circular is to promote the wider use of environmental and social considerations in public procurement with specific regard to the Climate Action Plan 2019 Circular 20/19
Arrangements concerning the use of central contracts put in place by the OGP. DPER This Circular concerns the use of central contracts and frameworks put in place by the OGP. Where public bodies do not use central procurement frameworks, they should be in a position to provide a value for money justification. Value for money justifications should take into account the full costs of running a public procurement competition. Circular 16/13
Initiatives to assist SMEs in Public Procurement DPER This Circular is designed to further enable SMEs in competing for public contracts. This Circular should be read in conjunction with the Public Procurement Guidelines for Goods and Services and the Capital Works Management Framework as appropriate. Circular 05/23
Procurement of Legal Services and Managing Legal Costs DPER This Circular reminds public bodies of their obligations to ensure that their procurement of legal services complies with the rules and guidelines on public procurement. It also outlines appropriate competitive procedures that can be used in the engagement of legal services and sets out a number of approaches and tools for public bodies to use in managing legal costs. Circular 05/13
Tax Clearance Procedures for Public Contracts Dept. of Finance This Circular sets out the requirement that public contracts may not be awarded, nor payments be made, unless the contractor holds a current Tax Clearance Certificate from the Irish Revenue Commissioners. Circular 43/06

Appendix 2 – Analysis of expenditure

(based on 2024 expenditure)

Table 1 – Income and expenditure analysis

Item Total (€) Description
Income 12,472,028 Authority income comes from occupational pension scheme and PRSA fees.
Expenditure 11,301,481 Salaries, rent, professional fees, capital expenditure, etc.

Table 2 – Expenditure – analysed by expenditure not subject, and subject to procurement

Item Total (€) % Description
Expenditure not subject to procurement 9,034,558 80% Predominantly relates to salaries, accommodation costs and corporate subscriptions.
Expenditure subject to procurement 2,266,923 20% Details shown in table 3.
Total expenditure 11,301,481 100%  

Table 3 – Expenditure subject to procurement, by category

Item Total (€) % Description
General administration 1,134,198 50% IT support and maintenance contracts, insurance, stationery, phones.
Professional fees 631,906 28% IT, legal, research, pensions consultancy and project work.
Information and publicity 231,425 10% Website, advertising and printing.
Training and education 139,995 6% Staff training in-house and external.
Depreciation on capital expenditure 129,399 6% Software systems development, computer and office equipment, and leasehold improvements.
Total expenditure subject to procurement 2,266,923 100%  

Appendix 3 – Procurement action plan 2025 – 2027

The Procurement action plan sets out practical, time limited measures the Procurement team within the Operations unit will undertake to improve routine procurement processes.

No Action Output/result Responsibility Timeframe
1 Review the Corporate procurement register monthly to ensure:
  • contracts are renewed on time or new contracts put in place.
  • expenditure under contracts is in line with estimates.
  • Contracts are extended or re- tendered in a timely manner.
  • Expenditure under a contract does not exceed the estimated value of the contract or breach thresholds.
Procurement team Monthly
2 Remind each Unit when a contract is up for renewal or replacement. Contracts will be put in place in a timely manner. Procurement team Ongoing
3 Publish a list of all contracts awarded with a value over €25,000 on the website with associated details. Increased transparency and compliance with the Freedom of Information Model Publication Scheme. Procurement team Quarterly
4 Publish a list of all purchase orders over €20,000 on the website with associated details. Increased transparency and compliance with the Public Sector Reform Plan. Procurement team Quarterly
5 Publish award notices for Authority tenders on eTenders.
  • Publication of award notices for all Authority tenders are up to date.
  • Tenders are closed as appropriate.
Procurement team Ongoing
6 Review the Corporate Procurement Plan. The Corporate Procurement Plan published to the website is up to date. SMT Annually by end Q4
7 Review the Authority’s Procurement procedures manual. The Authority’s procurement procedures manual published to the intranet is up to date. Procurement team Annually by end Q4